Please provide minutes of meetings, emails, documents, and transcripts that mention the cost of upgrading the New Hamburg wastewater treatment plant, or if the treatment plant can not be upgrade, please provide the studies and cost estimates to connect the site to the Kitchener sewage system.
| # | Rec | Name of Record | Date | To Be Rel | ✓ | # pages | Desc | Desc | Desc | Desc | Desc | Desc |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 5 | Email correspondence involving Township, Region of Waterloo and Ministry (Government of Ontario) | ----- | 7 | 17. Upgrade of wastewater treatment & pipeline | 18. Financing of land | 19. Budget for Township, Prov, & Fed | |||||
| 2 | 7 | Meeting Invitation | ----- | 2 | 8. Alternate sites | 17. Upgrade of wastewater treatment & pipeline | 18. Financing of land | 19. Budget for Township, Prov, & Fed | ||||
| 3 | 11 | Email correspondence involving Township, Region of Waterloo and Ministry (Government of Ontario) | ----- | 6 | 8. Alternate sites | 17. Upgrade of wastewater treatment & pipeline | 18. Financing of land | 19. Budget for Township, Prov, & Fed | ||||
| 4 | 19 | Email correspondence involving Ministry (Government of Ontario) and Township | ----- | 4 | 9. Industry water consumption | 17. Upgrade of wastewater treatment & pipeline | 18. Financing of land | 19. Budget for Township, Prov, & Fed | ||||
| 5 | 31 | Email correspondence involving Ministry (Government of Ontario) , Township and Region of Waterloo | ----- | 4 | 9. Industry water consumption | 17. Upgrade of wastewater treatment & pipeline | 18. Financing of land | 19. Budget for Township, Prov, & Fed | ||||
| 6 | 32 | Email correspondence involving Ministry (Government of Ontario), Township and Region of Waterloo | ----- | 4 | 9. Industry water consumption | 17. Upgrade of wastewater treatment & pipeline | 18. Financing of land | 19. Budget for Township, Prov, & Fed | ||||
| 7 | 33 | Email correspondence involving Ministry (Government of Ontario), Township and the Region of Waterloo | ----- | 5 | 9. Industry water consumption | 17. Upgrade of wastewater treatment & pipeline | 18. Financing of land | 19. Budget for Township, Prov, & Fed | ||||
| 8 | 36 | Email correspondence involving Ministry (Government of Ontario), Township and Region of Waterloo | ----- | 2 | 9. Industry water consumption | 17. Upgrade of wastewater treatment & pipeline | 18. Financing of land | 19. Budget for Township, Prov, & Fed | ||||
| 9 | 88 | Email correspondence involving Ministry (Government of Ontario), Region of Waterloo and Township | ----- | 5 | 17. Upgrade of wastewater treatment & pipeline | 18. Financing of land | 19. Budget for Township, Prov, & Fed |